A vision for the future

We would love for you to follow along each step of the way as we rejoice in what God has done and trust Him to provide for the future.

You can download a copy of the complete vision plan (Next Steps Book) HERE. In the meantime, please review the most recent developments and the next pertinent projects.

If you would like to partner with us by helping us take the next step financially, click on the "Donate" button below for secure credit card or PayPal processing. You can designate for a specific project or simply to "Next Steps." Thank you for your support of Peniel Bible Camp!




Current progress - STEPS 1-2

Wastewater Treatment Plant
  • Repairing existing system components
  • Increase operational efficiency with modern equipment
  • Meet current regulations to ensure compliance
  • Maintain functional capacity for the foreseeable future

Cost estimate: $40,000

Funding status: FULLY FUNDED

COMPLETED!!

Ashbrook Hall renovation
  • Build interior wall to divide the space
  • Meeting room with padded chairs and new audiovisual equip.
  • Dining room with tables/chairs and buffet-style meals
  • Climate control for both new areas and the kitchen

Cost estimate: $120,000

Funding status: FULLY FUNDED

COMPLETED!!

Youth cabin renovation
  • Upgrade 4 of the current youth cabins
  • Remodel interior and exterior with new doors, windows, etc.
  • Insulate and climate control
  • Add bathrooms and showers to each

Cost estimate: $120,000

Funding status: FUNDED

Estimated completion: Winter 2025-26

Staff housing
  • Identify locations in current campground area
  • Prepare sites for houses (modulars)
  • Address infrastructure needs
  • Build/remodel up to three staff housing units

Cost estimate: up to $360,000

Funding status: $265,000 funded and pledged

Estimated completion: 2026-2027

Future projects - STEP 3

Kitchen upgrade (1 of 3)
  • Begin replacement of major equipment
  • Remodel/update interior space 
  • Reconfigure layout for efficiency

Cost estimate: $50,000

Funding status : Funded

Estimated completion: 2026 (equipment already replaced)

Ashbrook Hall exterior
  • Construct steps/pathways on hill for safety
  • Add firepit and seating at the lakefront
  • Rebuild/expand small dock

Cost estimate: $40,000

Funding status: None

Estimated completion: 2027

New cabin (1 of 7)
  • Build new cabin near the 4 renovated cabins
  • Use previous design as template
  • Finishes this cabin "zone"

Cost estimate: $80,000

Funding status: None

Estimated completion: 2027

RV lots
  • Designate 4 spots beside new cabin area
  • Clear and prep areas
  • Pour pads and hook up infrastructure

Cost estimate: $20,000

Funding status: $10,000

Estimated completion: 2027